What actually wears in a chute
A chute rarely wears evenly. The damage is concentrated where the material lands, where it changes direction and where it slides fastest. Lining the whole chute to the same thickness is the most common way to overspend on a liner and still replace it early.
Walk the chute before you order. Mark the polished areas (sliding abrasion), the cracked or dented areas (impact) and the grooves (trapped material). That map decides the plate, the build-up and the layout.
Where to put which plate
| Impact point under the feed | Thickest build-up, or a separate impact plate. This is where cracks start, so the liner needs backing stiffness as much as hardness. |
| Chute floor | Continuous sliding abrasion - the highest wear zone. Full-length plates with the wear direction, not a patchwork. |
| Side walls | Lower walls wear; upper walls usually do not. Step the thickness down as the wear falls off. |
| Transition and discharge | Turbulence and edge loading. Radius the plate or use a formed section rather than forcing a flat plate into a curve. |
| Hopper walls | Steady sliding flow with less impact - a bimetallic plate with a moderate wear layer usually outlasts a thicker mild-steel liner at lower weight. |
Layout rules that decide liner life
- Overlap with the flow. The downstream plate laps over the upstream one; a lip facing the material is a wear point and a trap.
- Keep joints off the impact point. Move a seam 100 mm rather than land it where the material strikes.
- Stagger the courses. Brick-style stagger stops a continuous seam opening up across the chute.
- Leave a small gap for thermal movement on hot duty, and pack it so material cannot enter.
- Mark the plates. Number them to the drawing so the set goes back in the same order after the first reline.
Build-up by duty
| Light sliding | 4+4 mm - small chutes, low headroom, fine material. |
| General chute and hopper | 6+4 mm - the usual starting point for a steady sliding flow. |
| Coarse material, longer interval | 8+6 mm - the common heavy-duty request at transfer points. |
| Large lumps, high wear allowance | 10+10 mm - only where the structure can carry the weight. |
Build-ups are quoted as wear layer + backing and confirmed against the drawing. If you are unsure, send the old plate thickness and how long it lasted; the wear rate settles it faster than a table.
Installation checklist
- Check the structure is flat where the plate seats - a rocking plate works loose.
- Fit the impact plate first, then work downstream so laps close in the flow direction.
- Torque bolts to the drawing and re-check after the first shift.
- Weld only where the drawing allows; heat from welding can affect the wear layer edge.
- Photograph the finished lining and file it with the plate numbers for the next reline.
What to send for a liner quote
- Chute or hopper drawing, or a marked-up photo with plate outlines.
- Material handled, lump size, drop height, wet or dry, temperature.
- Plate thickness if specified, plus hole size and countersink detail.
- Quantity per chute and how many chutes in the programme.
FAQ
- What thickness of wear plate does a chute need? It depends on the material, the drop height and the interval you want between stops. Measure the wear rate of the liner being replaced, decide how many times longer it must last, and scale the wear layer - not the backing. A chute handling coarse ore at a transfer point usually needs more wear allowance than a hopper wall with a steady sliding flow.
- Should the liner cover the whole chute or only the wear zones? Line the zones that actually wear: the impact point under the feed, the floor and the lower side walls. Covering the whole chute with the same thickness wastes money on the upper walls and adds weight the structure has to carry.
- How should plates overlap at joints? Overlap in the direction of flow so material cannot catch an edge. Put the downstream plate over the upstream one, keep the step as small as the plate thickness allows, and never leave a lip facing the flow.
- Bolted or welded liners - which is better? Bolted or countersunk liners for chutes that will be relined; weld-on or plug-welded liners where the plate is permanent and the wall can take the welding. Impact zones often use both: bolts to hold, welds to stop the plate working loose.
- Can you supply the liner as a kit for one chute? Yes. Send the chute drawing or a marked-up photo with plate outlines and hole positions. We cut, drill and mark each plate so the set can be fitted in order without cutting on site.
- Do you supply the bolts and fixings? We supply the plates drilled to the drawing, including countersinks and keyways. Fixings are normally called out on the drawing; tell us the bolt size and we will match the hole detail.